8 Units of SCB13-630kVA Dry-Type Transformers for a Biosafety Laboratory in Germany

 

Project Overview

HBTP supplied 8 units of SCB13-630/10 transformers for a BSL-4 high-containment biosafety research laboratory in Munich, Germany. The project represents a significant deployment in the biomedical research sector, requiring transformers engineered for reliable operation under demanding conditions.

Project Background

A BSL-4 (Biosafety Level 4) laboratory handles the most dangerous pathogens, requiring absolute reliability in power supply for containment systems, air handling, and life support. Any power interruption could compromise biosafety, making 2N redundancy essential.

Customer Requirements

630kVA dry-type transformers with 2N redundancy configuration, critical lab-grade power quality, F1 fire resistance, low noise for laboratory environment, compliance with German DIN standards and BMBF biosafety regulations, and seamless UPS integration.

Our Solution

HBTP supplied its SCB13-series transformers, engineered specifically for biomedical research applications. The high-quality CRGO silicon steel core with step-lap mitered joints minimizes no-load losses, while copper windings provide enhanced short-circuit withstand capability and long service life.

Parameter Specification
Model SCB13-630/10
Capacity per Unit 630 kVA
Voltage Ratio 10 / 0.4 kV
Cooling ANAF
Efficiency SCB13
Standard IEC 60076-11
Reliability 2N Redundancy
Containment BSL-4 Support
Power Quality Critical Lab Grade

Quality & Testing

All units passed extended reliability testing and power quality analysis. Redundancy switchover testing verified zero-interruption transfer between transformer feeds. BSL-4 containment power requirements were verified in coordination with the lab's safety team.

Delivery & Installation

The 8 units (4 per redundant feed) were delivered and commissioned with strict adherence to laboratory construction protocols. HBTP provided 24/7 on-call support during the lab's initial activation phase.

8
Units Supplied
2N
Redundancy
BSL-4
Containment

Project Outcomes

All 8 transformers were successfully energized and are operating at rated capacity. The project was completed on schedule, and the customer has reported excellent performance with no unplanned outages attributed to transformer equipment. HBTP's reliable power distribution solution has contributed to the project's overall success and operational efficiency.