15 Dry-Type Transformers + 6 Box-Type Substations for a 2,000-Bed Hospital in the UAE
Project Overview
HBTP supplied 15 + 6 substations units of SCB13-1250/10 transformers for a 2,000-bed tertiary care hospital complex in Abu Dhabi, UAE. The project represents a significant deployment in the healthcare sector, requiring transformers engineered for reliable operation under demanding conditions.
Project Background
Modern hospitals require exceptionally reliable power distribution to support critical care equipment, operating theaters, and life-support systems. This 2,000-bed facility is one of the largest medical centers in the Middle East, demanding N+1 redundancy, low noise levels, and fire-safe construction throughout.
Customer Requirements
Dry-type F1 fire-resistant transformers, 1250kVA capacity, ultra-low noise (≤55dB(A)), 10kV/0.4kV ratio, IEC 60076-11 compliance, and box-type substations for outdoor installation with 50°C ambient rating for the UAE climate.
Our Solution
HBTP supplied its SCB13-series transformers, engineered specifically for healthcare applications. The high-quality CRGO silicon steel core with step-lap mitered joints minimizes no-load losses, while copper windings provide enhanced short-circuit withstand capability and long service life.
| Parameter | Specification |
|---|---|
| Model | SCB13-1250/10 |
| Capacity per Unit | 1250 kVA |
| Voltage Ratio | 10 / 0.4 kV |
| Cooling | ANAF |
| Efficiency | SCB13 |
| Standard | IEC 60076-11 |
| Noise | ≤ 55 dB(A) |
| Fire | F1 Self-extinguishing |
| Redundancy | N+1 |
Quality & Testing
Special attention was given to sound level testing, with each transformer measured in an acoustic chamber to verify the ≤55dB(A) requirement. All units passed partial discharge tests at ≤10 pC and F1 fire resistance certification.
Delivery & Installation
The equipment was delivered in phased shipments to align with the hospital's construction timeline. HBTP provided on-site commissioning support and conducted 72-hour load tests before hospital opening.
Project Outcomes
All 15 + 6 substations transformers were successfully energized and are operating at rated capacity. The project was completed on schedule, and the customer has reported excellent performance with no unplanned outages attributed to transformer equipment. HBTP's reliable power distribution solution has contributed to the project's overall success and operational efficiency.
Need a Custom Transformer Solution?
Contact our engineering team for a tailored quote based on your project specifications.
Request a Quote